Solar Energy Corporation of India Limited (SECI), a Navratna public sector enterprise under the Ministry of New and Renewable Energy (MNRE), has issued a Request for Empanelment (RfE) to onboard manufacturers, suppliers, integrators, and aggregators of grid-interactive Battery Energy Storage Systems (BESS). Issued on November 17, 2026, the tender aims to establish a pre-qualified vendor pool to support the growing deployment of utility-scale energy storage projects across India and strengthen the integration of renewable energy into the power grid.
The empanelment process will follow a two-stage mechanism. In Stage-I, SECI will assess applicants based on their technical and financial qualifications without requiring price bids. Selected bidders will be classified into four categories according to their eligible project procurement capacities. Tier I covers projects up to 100 MWh, Tier II covers above 100 MWh up to 300 MWh, Tier III covers above 300 MWh up to 600 MWh, and Tier IV covers above 600 MWh up to 1,000 MWh. Vendors qualifying for a higher tier will automatically become eligible for all lower tiers.
Under Stage-II, SECI will issue project-specific Requests for Quotations (RfQs) to empaneled vendors whenever storage procurement requirements arise. Contracts will be awarded through an Electronic Reverse Auction (e-RA). The empanelment will remain valid for one year from its effective date, although selection will not guarantee any minimum business commitment.
The tender follows a rolling submission process without a fixed overall closing date. Bidders must report document discrepancies within 20 days of the RfE issuance. Applications can be submitted by the last working day of every month until SECI announces termination of the process. Bid openings will take place on the first working day of the following month. Submitted bids must remain valid for 12 months.
Applicants are required to pay a non-refundable processing fee of ₹5,000 plus 18% GST. However, Micro and Small Enterprises with valid UDYAM registration are exempt. No Earnest Money Deposit (EMD) is required during the initial bidding stage. Selected vendors must subsequently provide an Empanelment Bank Guarantee ranging from ₹1.86 crore for Tier I to ₹18.60 crore for Tier IV. Annual empanelment fees range from ₹25,000 to ₹1 lakh, excluding GST.
SECI also permits alternative financial instruments, including Payment on Order Instruments from REC or PFC and compliant Insurance Surety Bonds.
The tender does not prescribe a fixed Performance Bank Guarantee amount. Instead, the Contract Performance Guarantee will be specified in individual project RfQs. Liquidated damages can reach 5% of the contract price each for supply and commissioning delays. Suppliers choosing an optional 10% interest-free mobilization advance must also submit a separate bank guarantee covering 110% of the advance amount.