A certificate of origin is not enough to guarantee financing under new US battery procurement rules.
Under the One Big Beautiful Bill Act (OBBBA), projects that begin construction after Dec. 31, 2025, must meet new foreign entity of concern (FEOC) restrictions to claim US federal clean energy tax credits. For standalone storage, the principal credit is the Clean Electricity Investment Tax Credit (ITC), found in Section 48E. Separate rules apply to the Clean Electricity Production Tax Credit (PTC), found in Section 45Y, and the Advanced Manufacturing Production Credit (Section 45X). Put simply, a project cannot source too much equipment from suppliers owned, controlled, or influenced by foreign governments. The statute calls these suppliers “prohibited foreign entities” (PFEs), and the IRS interim guidance, Notice 2026-15, sets out how compliance is measured.
The OBBBA preserves BESS credit eligibility into the next decade, but in 2026, energy storage projects are subject to Prohibited Foreign Entity (PFE) and Material Assistance Cost Ratio (MACR) regulations. At the same time, utility-scale systems frequently rely on lithium iron phosphate (LFP) cells predominantly produced outside the United States.
Tax equity investors, transfer credit buyers, lenders, and tax credit insurers now require actual evidence of PFE compliance before closing. Supplier certification is already proving less certain than previously expected.
Compliance framework
PFE compliance involves proving that the claiming taxpayer is not a PFE, that the project does not exceed permitted material assistance from PFEs, and that no payments or contractual rights give a PFE effective control. Projects that began construction before 2026 generally fall outside the material assistance test, a position tax counsel should confirm.
The MACR is the result of relevant direct costs minus PFE-attributable direct costs, divided by relevant direct costs. The cost base is the manufactured products and components incorporated into the project, not total capital expenditure (capex). For BESS projects beginning construction in 2026, the MACR must be at least 55% (no more than 45% PFE-attributable), rising to 60% in 2027, 65% in 2028, 70% in 2029, and 75% from 2030. Notice 2026-15 provides three interim safe harbors – Identification, Cost Percentage, and Certification – to help establish each component’s cost and PFE status.
The taxpayer generally uses its own acquisition cost or may apply the Identification and Cost Percentage safe harbors, which draw on tables published in Notice 2025-08. Using those does not mean domestic content compliance demonstrates PFE compliance. Battery cells carry the largest cost share, so cell sourcing is often decisive.
Under the Certification safe harbor, the taxpayer may rely on a qualifying certification from its direct supplier, signed under penalties of perjury and retained for at least six years. Section 6695B penalizes suppliers whose inaccurate certifications lead to a disallowed credit. Traceability is not a separate safe harbor, but it can test a certification’s factual basis and identify evidence gaps.
Limits of certification
Certifications are hard to obtain. Facing the perjury standard and Section 6695B penalties, suppliers and their counsel are increasingly unwilling to sign without substantial qualifications, leaving a greater portion of the risk with the taxpayer.
A certificate attests to facts the buyer cannot independently observe. Some PFE indicators are public, such as headquarters location, state ownership, or a government entity listing. Others, including ownership, debt, appointment rights, licensed intellectual property, and critical supply agreements, are private. Supplier-cooperative diligence can surface the documents, but classifying an entity remains a legal determination.
The same commercial cell model may be manufactured at different facilities or supplied through different legal entities, each with its own ownership and control structure, so the model alone may not establish project-specific PFE treatment. Suppliers are also restructuring, and the rules are still evolving. Battery management system (BMS) hardware sourced from a PFE affects the MACR, while BMS software, remote access, and long-term service agreement provisions raise unresolved effective-control questions. A certification is a snapshot of a moving object that is accurate when signed, but potentially insufficient by the time the credit is examined.
Risk allocation
Exposure for PFE non-compliance rests with the claiming taxpayer, typically the project owner and tax equity investor, and with transfer credit buyers under Section 6418. The OBBBA also extended the Internal Revenue Service (IRS) assessment period for material assistance errors to six years and tightened accuracy-related penalties for MACR overstatements. Documentation must remain defensible years into operation, potentially under guidance that is more developed than that available at financial close.
Passing the MACR at procurement doesn’t end the analysis. For 10 years after a facility is placed in service, certain payments to a PFE under arrangements giving it effective control can trigger recapture of the ITC. Warranty, BMS software, licensing, O&M, commissioning, and replacement-parts arrangements need review throughout operation.
A supplier certification supports the taxpayer’s substantiation file and may provide recourse against the supplier, but it doesn’t shift disallowance risk. Tax equity providers and insurers increasingly review the documentation behind a certificate, and verified, factory-level traceability generally clears that diligence more efficiently.
Co-located solar and storage projects face different timelines and thresholds for each technology, so one site may require two qualification analyses, with attention to shared-cost allocation.
Verification process
Because qualifying certifications fall within a safe harbor, independent traceability diligence is not strictly required but, given the capital at stake, it is often worth the upfront investment to find weaknesses early. Independent verification typically works at two levels:
First is certificate review, confirming that each certification contains every element the Notice requires, and that supporting documentation validates its statements.
The second is traceability diligence. Factory audits, review of materials traceability and receiving records, witnessing of inline production, and confirmation that an original equipment manufacturer (OEM) traceability report applies to the project-specific equipment, particularly where the same cell is produced at multiple factories. Its depth is typically set by the tax equity provider or insurer.
Ultimately, PFE rules have made tax credit qualification a project-specific outcome that must be demonstrated and maintained throughout the asset’s lifecycle. Technical verification can help establish product identity, factory of origin, and production records.
Early on, project owners and their financing parties should define how PFE status will be established, and agree it with tax counsel and financing parties before supply agreements are executed. Traceability documentation and audit rights should be defined as contractual deliverables. Contractual controls should be in place on post-commissioning arrangements that could create effective control, and documentation retention covering the six-year assessment and certification-retention periods and the 10-year recapture period. For co-located projects, separate analyses are needed for each technology.