GERC Examines Proposal To Revise FY25 RPOs Amid Supply Constraints In Gujarat

Power Wattz Solar | Off Grid Solar Solutions | Battery Backups > News > Solar > GERC Examines Proposal To Revise FY25 RPOs Amid Supply Constraints In Gujarat
November 26, 2026 joeyxweber No Comments

Torrent Power Limited’s distribution arm for the Dholera Special Investment Region (SIR), TPL-D, has approached the Gujarat Electricity Regulatory Commission (GERC) seeking a revision of its Renewable Purchase Obligation (RPO) targets for the financial year 2024–25, citing a lack of renewable power supply and challenges associated with developing a new electricity distribution network. The petition, registered as Petition No. 2525 of 2025, raises questions about the applicability of revised renewable energy regulations to obligations arising from a financial year that has already concluded.

Oriana

Torrent Power stated that it commenced electricity distribution operations in Dholera SIR during FY 2023–24. As the region is still in its early stages of development, electricity demand and power sales have not yet reached stable levels. For FY 2024–25, the company reported a total energy requirement of 62.27 million units (MUs).

ReNew

Under the Gujarat Electricity Regulatory Commission’s Renewable Purchase Obligation Regulations, 2010, as amended in 2022, Torrent Power was required to procure 20.70% of its total electricity requirement from renewable energy sources. This represented a renewable power procurement obligation of approximately 12.89 MUs. The target included 8.55% from wind energy, 11.25% from solar energy, 0.10% from hydroelectric power and 0.80% from biomass and other renewable sources.

However, Torrent Power reported that it could procure only 0.082 MUs of renewable electricity through the power exchange during the financial year, representing approximately 0.13% of its total energy requirement. Consequently, the company faced an RPO shortfall of around 12.81 MUs.

In its petition, the company explained that entering into long-term renewable power purchase agreements was not commercially feasible because electricity demand in Dholera SIR had not stabilised. It also stated that it did not receive any supply offers from renewable energy generators throughout FY 2024–25. Additionally, the available hydroelectric capacity within Gujarat was reserved for state-owned distribution companies, limiting its access to this renewable energy source.

Torrent Power has therefore requested GERC to exercise its powers under Regulation 4.2 of the 2010 RPO Regulations, which allows the Commission to revise renewable purchase targets when compliance becomes difficult due to supply constraints beyond the control of a distribution licensee.

The petition has also raised a regulatory and legal question concerning the retrospective application of renewable purchase obligations. Torrent Power filed its petition on July 30, 2025, following a GERC directive issued in June 2025. At that time, the 2010 RPO Regulations, as amended, governed the financial year under consideration.

However, GERC notified its new RPO Regulations, 2025, on August 12, 2025, increasing the renewable purchase target for FY 2024–25 to 29.91%, equivalent to approximately 18.62 MUs. The revised framework also introduced a 1% Energy Storage Obligation (ESO).

During hearings held in May and September 2026, GERC directed Torrent Power to submit compliance information based on the 2025 regulations. The company submitted the required information without prejudice to its legal position but challenged the retrospective application of the revised regulatory framework.

Torrent Power argued that regulatory obligations applicable to a completed financial year should not be changed retrospectively through subsequently notified regulations. Citing Supreme Court judgments and the legal principle that the law does not compel anyone to perform an impossibility, the company maintained that its obligations should be assessed under the regulations applicable during FY 2024–25.

Following the Commission’s directions, Torrent Power published public notices in the Ahmedabad editions of The Indian Express, Sandesh and Divya Bhaskar on November 7, 2026. The company also uploaded its petition to its website, inviting objections and suggestions from stakeholders.

GERC will consider the petition and stakeholder submissions before issuing its final decision on the requested revision of Torrent Power’s FY 2024–25 renewable purchase obligations.